The construction of the R-SAH strategic substation is progressing successfully as planned. ADI Group, in cooperation with PDL Transformation, has achieved another milestone - the main gantry has been erected on the site of the future substation, which forms a key structural component for the connection to the 400kV transmission system.
The attached photos show the current state of construction - in addition to the erected portal on site, R-SAH also documents the ongoing work at CEZ Distribuce's ETU power plant, where coordinated modifications related to the connection of the new infrastructure are taking place.
The R-SAH substation is the first private facility of its kind in the Czech Republic, which will enable direct power output from ADI Group's large-scale wind and solar power projects to the 400 kV transmission system. This significantly increases the flexibility and capacity to connect new renewable resources in the region.
This step confirms ADI Group's commitment to contributing to the transformation of the Czech energy sector and to strengthening energy independence through modern, privately built infrastructure. Work on other parts of the project - including the installation of transformer arrays and the connection of individual RES - is progressing on schedule with the aim of commissioning in 2026.